Gym in a former shop: a step at the only street entrance

  • Building: Class 9b gym, change of use from a Class 6 shop with a new commercial fit out

  • Location: Inner north Melbourne

  • NCC edition: NCC 2022, Volume One

  • Area of NCC requirements: D1P1 access for people with a disability; D4D2, D4D3 and D4D4 with AS 1428.1

  • Raised by: The relevant building surveyor, in a request for further information

  • Year: 2026

The challenge

The tenancy has one principal pedestrian entrance, opening straight off the street footpath. The existing doorway sits up to 180 mm above the footpath with no step free path. D4D2 to D4D4 require an accessway through the principal pedestrian entrance, so the change of use could not be approved with the entrance as it stood.

The performance solution

Expert judgement and comparison with the Deemed to Satisfy Provisions showed that assisted access at the existing doorway meets D1P1:

  • A portable step ramp complying with Clause 10.6 of AS 1428.1 is kept on site. For a rise of up to 180 mm it is 1800 mm to 1900 mm long, so it is not steeper than 1 in 10, with a slip resistant surface, kerbs to both sides and a load rating suited to powered wheelchairs and mobility scooters.

  • The ramp is deployed with a clear 1500 mm landing at its base on the footpath and a clear 1500 mm landing inside the door, and it is stored beside the entrance so it can be set up quickly.

  • A call button is installed at the entrance between 900 mm and 1100 mm above the footpath, connected to reception, with International Symbol of Access signage advising that ramp assistance is available.

  • An employee management plan covers staff at reception during all opening hours, training in deploying the ramp and assisting people using mobility aids, clear protocols, regular review and emergency evacuation procedures.

  • Reception is near the entrance, so people arriving can be seen and helped promptly.

  • The report records that the solution depends on staff being present. If the gym moves to unstaffed 24 hour access, the report and management plan must be reviewed before those hours start.

Outcome

Final report issued to the relevant building surveyor in November 2026 for approval with the building permit.

Lesson for designers

Assisted access only works while someone is there to assist. Write the staffing assumption into the report itself, because a later switch to 24 hour fob access is exactly when these solutions stop working.

Related: Access performance solutions | Performance solution report

Need a performance solution for a similar problem? Request a fee proposal or phone 0407 560 708.