Building: Class 10b precast plunge pool serving a new double storey dwelling
Location: South east Melbourne
NCC edition: NCC 2025, Volume Two
Area of NCC requirements: H2P4 drainage from swimming pools (no Deemed to Satisfy Provisions apply)
Raised by: The relevant building surveyor, at design stage
Year: 2026
The challenge
NCC Volume Two has no Deemed to Satisfy Provisions for draining a swimming pool, so every new pool has to meet H2P4 by a performance solution. This pool is 6.0 m by 2.4 m and holds about 13.5 kL. It uses cartridge filtration with no regular backwashing, and the pool contractor drains it with a pump when needed.
The performance solution
Expert judgement, benchmarked against EPA guidance on pool water disposal and AS/NZS 3500.2, showed that sending all pool waste water to sewer meets H2P4:
A 100 mm sanitary drainage connection is installed near the pool equipment and connected to sewer. It stays closed with a removable sealed cap during normal operation.
To empty or partly drain the pool, water is pumped into that connection with the hose secured so it cannot overflow. Pool water is never pumped to stormwater, the street or neighbouring land.
Water used to clean the filter cartridges also goes to the sewer connection.
The work follows Clauses 13.22 and 12.8.7 of AS/NZS 3500.2, with non return valves and UV protection to any exposed PVC pipe.
The plumber obtains any approval needed from the water authority and provides a plumbing compliance certificate to the building surveyor.
The licensed plumber confirms the connection location on a drainage plan, and the pool contractor confirms the filter model, because the supplier calculation sheet listed a media filter rather than a cartridge.
Outcome
Report prepared in November 2026 and successfully accepted by the relevant building surveyor.
Lesson for designers
Every new pool needs this report, so plan for it at design stage. Settle the sewer connection point with the plumber before the permit, and check that the filter on the supplier paperwork matches the one actually being installed.